November 2015

Report Date
November 2015

Achievements in Last Period

  • Milestones planned assuming pilots with 2-3 services, sequentially, with review after each and final recommendations
  • Milestones pushed back to allow stakeholders to complete brief and estimates, and engage with ITI and Apps Directors.
  • Preparatory work for pilot infrastructure delayed by other ITI work, expected to be completed before end of December to allow config work to begin in January in line with proposed milestones.

 

Issues

  • No major issues.
  • Project team availability has been an issue due to holidays - PICCL raised 26/11 and milestone changes agreed with Project Sponsor.

 

Next Steps

  • Complete Project Brief and estimates, agree with stakeholders including directors of IS ITI and Apps.

 

Milestones (to be confirmed)

18-Dec-2015End of Planning
08-Jan-2016Build SCOM Pilot Infrastructure
21-Jan-2016Establish Virtual IS Monitoring Team(s)
04-Feb-2016Pilot Service 1 - Windows
03-Mar-2016Pilot Service 2 - Linux
07-Apr-2016Pilot Service 3 - Corporate
05-May-2016Recommendations
05-May-2016Delivery
19-May-2016Close
Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
GREEN
Overall
RED
Change Status
Activity
Approved budget
100.0 days
Activity this month
2.0 days
Activity this year
4.0 days
Activity to date
4.0 days
Estimate to complete current year
92.0 days
Estimate to complete future years
0.0 days

Project Info

Project
System Monitoring Pilot
Code
INF113
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
21-Oct-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
16-Sep-2016
Programme Priority
7
Overall Priority
Normal
Category
Discretionary