November 2015
- Report Date
- November 2015
Achievements in Last Period
- Milestones planned assuming pilots with 2-3 services, sequentially, with review after each and final recommendations
- Milestones pushed back to allow stakeholders to complete brief and estimates, and engage with ITI and Apps Directors.
- Preparatory work for pilot infrastructure delayed by other ITI work, expected to be completed before end of December to allow config work to begin in January in line with proposed milestones.
Issues
- No major issues.
- Project team availability has been an issue due to holidays - PICCL raised 26/11 and milestone changes agreed with Project Sponsor.
Next Steps
- Complete Project Brief and estimates, agree with stakeholders including directors of IS ITI and Apps.
Milestones (to be confirmed)
18-Dec-2015 | End of Planning |
08-Jan-2016 | Build SCOM Pilot Infrastructure |
21-Jan-2016 | Establish Virtual IS Monitoring Team(s) |
04-Feb-2016 | Pilot Service 1 - Windows |
03-Mar-2016 | Pilot Service 2 - Linux |
07-Apr-2016 | Pilot Service 3 - Corporate |
05-May-2016 | Recommendations |
05-May-2016 | Delivery |
19-May-2016 | Close |
- Approved budget
- 100.0 days
- Activity this month
- 2.0 days
- Activity this year
- 4.0 days
- Activity to date
- 4.0 days
- Estimate to complete current year
- 92.0 days
- Estimate to complete future years
- 0.0 days