August 2016

Report Date
August 2016

Achievements in Last Period

  • Recommendations Report distributed and feedback incorporated.
  • Closure report drafted.

 

Issues

  • Some disagreement on wording of report re: objectives and recommendations; Project Sponsor has given PM steer on how to reword to resolve this and has communicated intentions to colleagues in ITI.

 

Next Steps

  • Distribute closure report and incorporate feedback.
  • Project Closure.

 

Milestones

29-Aug-2016Recommendations
09-Sep-2016Close

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
BLUE
Change Status
Activity
Approved budget
40.0 days
Activity this month
3.0 days
Activity this year
3.0 days
Activity to date
39.0 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days

Project Info

Project
System Monitoring Pilot
Code
INF113
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
21-Oct-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
16-Sep-2016
Programme Priority
7
Overall Priority
Normal
Category
Discretionary