July 2016
- Report Date
- July 2016
Achievements in Last Period
- Recommendations Report drafted.
Issues
- Report not completed for review and feedback due to resource conflict on PM (complications on MVM009, and Annual Leave). Now expected w/c 08/08/16 with closure to follow when agreement reached on report.
Next Steps
- Distribute recommendations report.
- Project Closure.
- Approved budget
- 40.0 days
- Activity this month
- 2.0 days
- Activity this year
- 36.0 days
- Activity to date
- 36.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 1.7 days