October 2015

Report Date
October 2015

Achievements in Last Period

  • Project Website set up.
  • Initial meeting with stakeholders in ITI to review recommendations from INF107 and agree overall project scope.
  • PM has met with Project Sponsor to follow up on expectations for Project, potential candidate services for pilot.
  • Milestones to be planned assuming pilots with 2-3 services, sequentially, with review after each and final recommendations

 

Issues

  • No major issues.

 

Next Steps

  • Complete Project Brief and estimates, agree with stakeholders including directors of IS ITI and Apps.

 

Milestones (to be confirmed)

14-Nov-2015End of Planning
11-Mar-2016Delivery
27-Mar-2016Close
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
100.0 days
Activity this month
1.5 days
Activity this year
1.5 days
Activity to date
1.5 days
Estimate to complete current year
98.5 days
Estimate to complete future years
0.0 days

Project Info

Project
System Monitoring Pilot
Code
INF113
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
21-Oct-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
16-Sep-2016
Programme Priority
7
Overall Priority
Normal
Category
Discretionary