October 2015
- Report Date
- October 2015
Achievements in Last Period
- Project Website set up.
- Initial meeting with stakeholders in ITI to review recommendations from INF107 and agree overall project scope.
- PM has met with Project Sponsor to follow up on expectations for Project, potential candidate services for pilot.
- Milestones to be planned assuming pilots with 2-3 services, sequentially, with review after each and final recommendations
Issues
- No major issues.
Next Steps
- Complete Project Brief and estimates, agree with stakeholders including directors of IS ITI and Apps.
Milestones (to be confirmed)
14-Nov-2015 | End of Planning |
11-Mar-2016 | Delivery |
27-Mar-2016 | Close |
- Approved budget
- 100.0 days
- Activity this month
- 1.5 days
- Activity this year
- 1.5 days
- Activity to date
- 1.5 days
- Estimate to complete current year
- 98.5 days
- Estimate to complete future years
- 0.0 days