March 2015
- Report Date
- March 2015
All vists and demos for external and internals product completed. The team have started on final assessment, recommendation and report.
Achievements in Last Period
- Visit Imperial and assess - done
- Demo of Zenoss and assess - done
- Demo of SCOM and assess - done
- Assess potential of newRelic - done
Issues
- one Amber risks - last reviewed early April
Next Steps
- write report with recommentation for management
Milestones
29-Apr-2015 | Recommendation after Visits to Institutions |
11-May-2015 | Closure |
- Approved budget
- 60.0 days
- Activity this month
- 16.0 days
- Activity this year
- 45.0 days
- Activity to date
- 45.0 days
- Estimate to complete current year
- 14.0 days
- Estimate to complete future years
- 0.0 days