January 2015

Report Date
January 2015

The project milestones have been moved back further, in part due to Imperial not having availability until March, but also, the project team have decided to look at whether existing tools in use by Unix, Architecture and Edina coudl provide our solution.

This reduced the amount of time left to do the follow on project to procure/build a solution, so the effort estimated has been reduced in this year and moved to 15/16 and 16/17.

The staus of the project remains Green, but any further slippage would set it to Amber.

Achievements in Last Period

  • Sheffield visted and assessed
  • Visit Imperial by end of January - not achieved
  • Set up demo of EG
  • Confirm third institution to visit by end of January

Issues

  • Two Amber risks - last reviewed mid-November - no change and still pertinent

Next Steps

  • Demo of EG and assessment
  • Visit Imperial by end of March
  • Assess potential of Zenoss
  • Assess potential of SCOM
  • Assess potential of newRelic  

Milestones  

13-Mar-2015Optional - Visit a fourth institution write up outcomes
13-Mar-2015Visit Three Institutions and write up outcomes
10-Apr-2015Recommendation after Visits to Institutions
24-Apr-2015Accepted Solution
01-May-2015Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
60.0 days
Activity this month
3.0 days
Activity this year
24.0 days
Activity to date
24.0 days
Estimate to complete current year
34.0 days
Estimate to complete future years
0.0 days