January 2015
- Report Date
- January 2015
The project milestones have been moved back further, in part due to Imperial not having availability until March, but also, the project team have decided to look at whether existing tools in use by Unix, Architecture and Edina coudl provide our solution.
This reduced the amount of time left to do the follow on project to procure/build a solution, so the effort estimated has been reduced in this year and moved to 15/16 and 16/17.
The staus of the project remains Green, but any further slippage would set it to Amber.
Achievements in Last Period
- Sheffield visted and assessed
- Visit Imperial by end of January - not achieved
- Set up demo of EG
- Confirm third institution to visit by end of January
Issues
- Two Amber risks - last reviewed mid-November - no change and still pertinent
Next Steps
- Demo of EG and assessment
- Visit Imperial by end of March
- Assess potential of Zenoss
- Assess potential of SCOM
- Assess potential of newRelic
Milestones
13-Mar-2015 | Optional - Visit a fourth institution write up outcomes |
13-Mar-2015 | Visit Three Institutions and write up outcomes |
10-Apr-2015 | Recommendation after Visits to Institutions |
24-Apr-2015 | Accepted Solution |
01-May-2015 | Closure |
- Approved budget
- 60.0 days
- Activity this month
- 3.0 days
- Activity this year
- 24.0 days
- Activity to date
- 24.0 days
- Estimate to complete current year
- 34.0 days
- Estimate to complete future years
- 0.0 days