December 2014

Report Date
December 2014

Achievements in Last Period

  • Complete Questions, Answers and Scenarios for Visits - achieved
  • Visit Sheffield in December- achieved

Issues

  • Two Amber risks - last reviewed mid-November - no change and still pertinent

Next Steps

  • Visit Imperial by end of January
  • Confirm third institution to visit by end of January  

Milestones  

09-Jan-2015Confirm Site Visits with other Institutions
30-Jan-2015Optional - Visit a fourth institution write up outcomes
30-Jan-2015Visit Three Institutions and write up outcomes
27-Feb-2015Recommendation after Visits to Institutions
13-Mar-2015Accepted Solution
27-Mar-2015Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
60.0 days
Activity this month
7.0 days
Activity this year
21.0 days
Activity to date
21.0 days
Estimate to complete current year
39.0 days
Estimate to complete future years
0.0 days