November 2014

Report Date
November 2014

Achievements in Last Period

  • Complete Questions, Answers and Scenarios for Visits - not achieved. Not all the team have made their contributions yet.
  • Visit Sheffield in November - not achieved, but 16th december is confirmed
  • Visit Imperial by early December - unlikely - waiting to hear
  • Confirm third institution to visit by end of the Year - looking to visit Greenwich at same time as Imperial.

Issues

  • Two Amber risks - last reviewed mid-November - no change and still pertinent

 

Next Steps

  • Complete Questions, Answers and Scenarios for Visits
  • Visit Sheffield in December
  • Visit Imperial by end of January
  • Confirm third institution to visit by end of January  

Milestones  

10-Dec-2014Prepare Questions and Model Answers
09-Jan-2015Confirm Site Visits with other Institutions
30-Jan-2015Optional - Visit a fourth institution write up outcomes
30-Jan-2015Visit Three Institutions and write up outcomes
27-Feb-2015Recommendation after Visits to Institutions
13-Mar-2015Accepted Solution
27-Mar-2015Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
60.0 days
Activity this month
4.0 days
Activity this year
14.0 days
Activity to date
14.0 days
Estimate to complete current year
44.0 days
Estimate to complete future years
0.0 days