October 2014
- Report Date
- October 2014
Achievements in Last Period
- Capture feedback from Sheffield Hallam - Achieved
- ITI colleagues confirmed
- Set up two visits for October - Not Achieved
Issues
- no issues
- Two Amber risks - last reviewed end of September
Next Steps
- Complete Questions, Answers and Scenarios for Visits
- Visit Sheffield in November
- Visit Imperial by early December
- Confirm third institution to visit by end of the Year
Milestones
17-Nov-2014 | Confirm Site Visits with other Institutions |
17-Nov-2014 | Prepare Questions and Model Answers |
19-Dec-2014 | Visit Three Institutions and write up outcomes |
15-Jan-2015 | Optional - Visit a fourth institution write up outcomes |
23-Jan-2015 | Recommendation after Visits to Institutions |
06-Feb-2015 | Accepted Solution |
13-Feb-2015 | Closure |
- Approved budget
- 60.0 days
- Activity this month
- 2.7 days
- Activity this year
- 9.5 days
- Activity to date
- 9.5 days
- Estimate to complete current year
- 51.7 days
- Estimate to complete future years
- 0.0 days