October 2014

Report Date
October 2014

Achievements in Last Period

  • Capture feedback from Sheffield Hallam - Achieved
  • ITI colleagues confirmed
  • Set up two visits for October - Not Achieved

Issues

  • no issues
  • Two Amber risks - last reviewed end of September

 

Next Steps

  • Complete Questions, Answers and Scenarios for Visits
  • Visit Sheffield in November
  • Visit Imperial by early December
  • Confirm third institution to visit by end of the Year  

Milestones  

17-Nov-2014Confirm Site Visits with other Institutions
17-Nov-2014Prepare Questions and Model Answers
19-Dec-2014Visit Three Institutions and write up outcomes
15-Jan-2015Optional - Visit a fourth institution write up outcomes
23-Jan-2015Recommendation after Visits to Institutions
06-Feb-2015Accepted Solution
13-Feb-2015Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
60.0 days
Activity this month
2.7 days
Activity this year
9.5 days
Activity to date
9.5 days
Estimate to complete current year
51.7 days
Estimate to complete future years
0.0 days