June 2015

Report Date
June 2015

A final version of the recommendation report was discussed and was formally approved at meeting on 2nd June.

Achievements in Last Period

  • send report to management - done, and there is approval to proceed to pilot
  • close project - in progress

Issues

  • no open issues or risks

Next Steps

  • close project w/c 29th June

 

Milestones  

1-Jul-2015Closure

 

  •  
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
BLUE
Change Status
Activity
Approved budget
60.0 days
Activity this month
2.0 days
Activity this year
59.0 days
Activity to date
59.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days