Current project status Report Date RAG Budget Effort Completed Effort to complete November 2019 BLUE 25.0 days 25.8 days 0.0 Content Status Closed Current Stage Close Start Date Friday, 12 October 2018 Planning Date Friday, 5 April 2019 Delivery Date Thursday, 26 September 2019 Close Date Friday, 22 November 2019 Project information Project Code HSS026 Programme CAHSS Portfolio Projects Session 19/20 18/19 17/18 Organisational Unit College of Arts, Humanities and Social Sciences Project Management Office (if relevant) ISG PMO Responsibility Applications Development and Operations Project Category Discretionary Project Classification Run Funding Source Sponsor Funded by Fraser Muir Programme Priority 7 Overall Priority Normal