w/c 15th January 2018
During the weekly conference call the following points were noted
- Data Security
- The matter of access to the data has been escalated to the DWP and initial conversations have been positive
- Further meeting is scheduled and an update will be provided on 26/01/18
- It was noted that if access is not granted, discussions are on-going regarding alternatives
- Design Changes
- An agreed number of design changes have been agreed and are scheduled to be completed by mid-February incorporating
- Randomisation
- job suggestions turned on/off
- User acceptance testing is now scheduled to commence on 20th February
- Live launch scheduled for 1st March 2018
- An agreed number of design changes have been agreed and are scheduled to be completed by mid-February incorporating
- Specification on Randomisation requirements prepared by PM and circulated