w/c 11th February 2019

  • Weekly project conference call held
  • Meeting with JA/GP to plan out developments for 
    • API changes - specification to be created and forwarded to Ungeus
    • Prepare Test environment o receive amended data set 
    • Report to detail incoming data from Ingeus to ensure data is being received 
    • Migration of historic data from 29/12 to 16/01 
    • Database views 
  • Revised project milestones approved by WIS
  • API Development 
    • First specification forwarded to Ingeus on 15/02/19
    • Test system prepared to received data 
    • IW advised that Ingeus would be working on this early next week 

Project Info

Project
School of Economics Job Study
Code
HSS015
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Philipp Kircher
Current Stage
Deliver
Status
In Progress
Project Classification
Grow
Start Date
07-Jul-2016
Planning Date
09-Dec-2016
Delivery Date
31-Jan-2020
Close Date
21-Feb-2020
Overall Priority
Normal
Category
Discretionary