w/c 7th January 2019

  • Live Data Transfer 
    • Ingeus switched-on 28th December 2018
    • Initial review of data would indicate data being transmitted to Test system, as opposed to Live 
    • UoE / Ingeus developer to resolve live data transfer
    • UoE to investigate migrating data from Test to Live 
  • Weekly project conference call held
    • Advised that new project manger is being assigned to the project 
  • Noted that the SDD had been completed and forwarded to IS Apps Production Management
  • Phase 2 Development 
    • Ingeus have advised that the Go-Live/Release of the finished project into Live environment is currently scheduled for 28th February, with UAT and Regression testing starting two weeks earlier (on the 18th).

Project Info

Project
School of Economics Job Study
Code
HSS015
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Philipp Kircher
Current Stage
Deliver
Status
In Progress
Project Classification
Grow
Start Date
07-Jul-2016
Planning Date
09-Dec-2016
Delivery Date
31-Jan-2020
Close Date
21-Feb-2020
Overall Priority
Normal
Category
Discretionary