w/c 15th October

  • UAT
    • The final two JIRA's (35 and 52) have been closed
    • UAT for phase 1 has been completed
  • Outstanding JIRA's
    • review of remaining 7 JIRA's
  • Project Plan updated to take into account
    • dates for Phase 2
    • re-scheduled activity relating 
      • SDD and security checks
      • data download based on guestimate approval date for DWP
      • OLA and Deployment check lists
      • database views
  • Updated ASTA to reflect above changes, currently projecting 3 days over budget
  • Reviewed project risk register
  • Weekly project team conference call held

Project Info

Project
School of Economics Job Study
Code
HSS015
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Philipp Kircher
Current Stage
Deliver
Status
In Progress
Project Classification
Grow
Start Date
07-Jul-2016
Planning Date
09-Dec-2016
Delivery Date
31-Jan-2020
Close Date
21-Feb-2020
Overall Priority
Normal
Category
Discretionary