w/c 1st October 2018

  • User acceptance Testing
    • Currently little progress regarding testing due to technical issues.  Currently awaiting Ingeus to investigate
    • Ingues have advised that development resource will now be made available between 4th and 9th October, however there is no offer of contingency if the testing cannot be completed in the time period
    • The issue has been escalated to both the Project Sponsor and Senior Supplier
    • At the end of the week
      • 4 JIRA's have been closed
      • 14 JIRA's remain outstanding
  • Weekly teleconference held  to
    • Review Ingeus solution not that UOE job search functionality has been switched back-on.  Paul Muller confirmed no change and was as before
    • Discussion regarding UAT
      • agreed to progress UAT
      • further progress review on Monday with request to Ingeus to have alternative resource plan in place to support UAT extending over the period 9th October
  • Outstanding Activity details have been published on 04/10/18 and will be updated and circulated at the end of each day 
  • Project risk log updated
  • DWP
    • Currently waiting for DWP to forward license agreement to the Project Sponsor

Project Info

Project
School of Economics Job Study
Code
HSS015
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Philipp Kircher
Current Stage
Deliver
Status
In Progress
Project Classification
Grow
Start Date
07-Jul-2016
Planning Date
09-Dec-2016
Delivery Date
31-Jan-2020
Close Date
21-Feb-2020
Overall Priority
Normal
Category
Discretionary