w/c 19th March 2018

  • API Development
    • The API (v. 1.0.0-rc8) work has been completed and deployed to the test environment
  • Project team conference call
    • Further project delays after re-estimating development requirements.  Now scheduled for 25th May
    • Revised project plan with defined sprints highlighted and UOE requirements for testing
    • Still awaiting clearance from DWP over security questions
      • questions now relate to Ingeus and are anticipated to be completed within the next three weeks (allowing for Easter)

Project Info

Project
School of Economics Job Study
Code
HSS015
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Philipp Kircher
Current Stage
Deliver
Status
In Progress
Project Classification
Grow
Start Date
07-Jul-2016
Planning Date
09-Dec-2016
Delivery Date
31-Jan-2020
Close Date
21-Feb-2020
Overall Priority
Normal
Category
Discretionary