Report for July 2017

Report Date
July 2017

Achievements this period

  • Scheduled deployment date for Release 3 which will take place on 7th August
  • Release 3 planning meeting held to prepare for deployment

Issues

Open Issues

  • The document upload function could not be completed within the Maintenance iteration as it had a dependency on the Python resilient file store, which faced technical challenges in its development and was subject to further review by Tech Management and ITI.  Following negotiation with the Product Owner it was agreed the project will schedule a Release 3 to incorporate this function plus a small bug fix that arose following the Maintenance iteration.  There is sufficient budget available to accommodate this final release.

Next Steps

  • Confirm OLA signoff by specified signatories in CAHSS and Student Systems
  • Deploy Release 3 on 7th August
  • Draft closure report
  • Close project
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
275.0 days
Activity this month
5.7 days
Activity this year
250.8 days
Activity to date
266.2 days
Estimate to complete current year
0.0 days
Estimate to complete future years
8.8 days

Project Info

Project
CAHSS School and Programme Quality System
Code
HSS014
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Ben Armstrong
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Start Date
23-Jun-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
15-Sep-2017
Category
Discretionary