Report for December 2015
- Report Date
- December 2015
Achievements in Last Period
- Issued the final analysis and requirements documentation to project stakeholders including the members of the HSS QA Committee; the analysis has received positive feedback and will provide a good platform from which to undertake the system implementation project.
Issues
- The Completion milestone date has passed as not all the sign-offs for project closure were able to be confirmed prior to the University's Christmas break; the remaining sign-offs will be confirmed during the first week of January 2016.
Next Steps
- Close project
- Approved budget
- 50.0 days
- Activity this month
- 1.0 day
- Activity this year
- 25.3 days
- Activity to date
- 48.5 days
- Estimate to complete current year
- 1.5 days
- Estimate to complete future years
- 0.0 days