Report for December 2015

Report Date
December 2015
Achievements in Last Period
  • Issued the final analysis and requirements documentation to project stakeholders including the members of the HSS QA Committee; the analysis has received positive feedback and will provide a good platform from which to undertake the system implementation project.

Issues

  • The Completion milestone date has passed as not all the sign-offs for project closure were able to be confirmed prior to the University's Christmas break; the remaining sign-offs will be confirmed during the first week of January 2016.   

Next Steps

  • Close project
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
50.0 days
Activity this month
1.0 day
Activity this year
25.3 days
Activity to date
48.5 days
Estimate to complete current year
1.5 days
Estimate to complete future years
0.0 days

Project Info

Project
HSS Course and Programme Monitoring System Requirements
Code
HSS010
Programme
CAHSS Portfolio Projects
Project Manager
Ben Armstrong
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Start Date
14-May-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
11-Jan-2016
Category
Discretionary