Report for October 2015

Report Date
October 2015
Achievements in Last Period
  • Collated feedback about draft system design considerations from the September College QA Committee meeting

Issues

  • The Business Analysis milestone has not been formally signed off by the project sponsor but will be signed off this week on further request.  In the meantime this does not present an issue to making progress with the project as we move towards confirming the high level business requirements.

Next Steps

  • Present proposed product vision, roles, process and high level requirements at the November College QA Commitee meeting
  • Decide on preferred software development methodology
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
50.0 days
Activity this month
3.2 days
Activity this year
18.4 days
Activity to date
41.6 days
Estimate to complete current year
8.4 days
Estimate to complete future years
0.0 days

Project Info

Project
HSS Course and Programme Monitoring System Requirements
Code
HSS010
Programme
CAHSS Portfolio Projects
Project Manager
Ben Armstrong
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Start Date
14-May-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
11-Jan-2016
Category
Discretionary