Report for September 2015
- Report Date
- September 2015
Achievements in Last Period
- Presented findings to college level QA representatives
- Attended September 16th College QA Committee, providing feedback to School QA Directors and setting them some high level system design questions arising from the analysis
Issues
- The Business Analysis milestone has passed, however the initial analysis has been completed. Project Manager will ask the project sponsor to sign off the milestone, this is not seen as a major issue as it does not prevent us from moving into the business requirements stage
Next Steps
- Prepare for attending next College QA Committee (due to take place on November 4th) to gain agreement for product vision and target process
- Approved budget
- 50.0 days
- Activity this month
- 4.5 days
- Activity this year
- 15.2 days
- Activity to date
- 38.4 days
- Estimate to complete current year
- 11.6 days
- Estimate to complete future years
- 0.0 days
