Report for July 2015

Report Date
July 2015
Achievements in Last Period
  • Completed meetings with the QA Directors for each school
  • Signed off Planning Stage
  • Engaged with Agile coach to support project activity

Issues

  • None noted

Next Steps

  • Complete business analysis document and share with project sponsor and stakeholders
  • Plan next stage of project
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
50.0 days
Activity this month
10.1 days
Activity this year
23.0 days
Activity to date
23.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
27.0 days

Project Info

Project
HSS Course and Programme Monitoring System Requirements
Code
HSS010
Programme
CAHSS Portfolio Projects
Project Manager
Ben Armstrong
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Start Date
14-May-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
11-Jan-2016
Category
Discretionary