Organisation

 

Work/Task Breakdown

TaskEstimate (days)Team
DevTech Consultation with Desktop Services Risk 1 is not having a way of automatically deploying the system to HSS desktops. Iain Fiddes has therefore recommended that the first task should be to consult with Desktop Services to confirm that they can do this2DevTech
Building the new OCS system on the VM  
o   Technical proposal (TAD, BRD, Operational Specification)5DevTech
o   Build5DevTech
o   Config, preparation and Validation5DevTech
o   There is no expectation of disaster recovery  - will need a back-up but no DR – will restore from tape0N/A
o   Contingency = 10 days10DevTech
Handover to IS Apps  Production Management0.5DevTech
 0.5TechMan
Project Management4Project Services
TOTAL32 

Resources Skills and Cost

TeamEstimate (days)
Project Services4
Development Technology27.5
Technology Management0.5
Total32

 

Project Info

Project
OCS Inventory for HSS
Code
HSS005
Programme
CAHSS Portfolio Projects
Project Manager
Craig Middlemass
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Start Date
06-Jun-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Jan-2015
Programme Priority
2
Overall Priority
Normal
Category
Discretionary

Documentation