Report for August 2014

Report Date
August 2014

Achievements in Last Period

  • Agreed the project brief
  • Draft and issued recommendation paper including requirements
  • Engaged with 2 vendors for Events Management to guage the level of cost

Issues

  • Conflicts for PM time with the Timetabling project causing slow down of analysis and write up

Next Steps

  • Sign off the recommendation
  • Close the project

Milestones

Target dateTitleComplete
05-Sep-2014Review and sign off recommendationNo
05-Sep-2014Close ProjectNo
05-Sep-2014Agree action and next steps with all business areasNo

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
10.0 days
Activity this month
2.3 days
Activity this year
2.3 days
Activity to date
9.1 days
Estimate to complete current year
1.3 days
Estimate to complete future years
0.0 days

Project Info

Project
CRM for HSS Options appraisal
Code
HSS004
Programme
CAHSS Portfolio Projects
Project Manager
Craig Middlemass
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Start Date
06-Jun-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
19-Sep-2014
Programme Priority
2
Overall Priority
Normal
Category
Discretionary

Documentation