Report for August 2014
- Report Date
- August 2014
Achievements in Last Period
- Agreed the project brief
- Draft and issued recommendation paper including requirements
- Engaged with 2 vendors for Events Management to guage the level of cost
Issues
- Conflicts for PM time with the Timetabling project causing slow down of analysis and write up
Next Steps
- Sign off the recommendation
- Close the project
Milestones
| Target date | Title | Complete |
|---|---|---|
| 05-Sep-2014 | Review and sign off recommendation | No |
| 05-Sep-2014 | Close Project | No |
| 05-Sep-2014 | Agree action and next steps with all business areas | No |
- Approved budget
- 10.0 days
- Activity this month
- 2.3 days
- Activity this year
- 2.3 days
- Activity to date
- 9.1 days
- Estimate to complete current year
- 1.3 days
- Estimate to complete future years
- 0.0 days