Report for September 2015
- Report Date
- September 2015
Achievements in This Period
- HR consulted wider stakeholders for feedback on the calculator. The feedback received was very positive and three JIRAs have been raised for minor changes before LIVE deployment. These minor changes have been resourced to complete w/c Oct 5
- Confirmation was obtained that the Calculator will inherit the banner image from the HR Site in EdWeb and therefore an image specifically for the Calculator is not required.
Issues
- None
Next Steps
- Complete final UAT for 3 JIRAs
- Update payscales information as part of deployment to LIVE
- Deploy
- Close
Milestones
16-Oct-2015 | Complete UAT & re-work |
24-Nov-2015 | Deploy HR Reward Calculator to LIVE |
01-Dec-2015 | Deployment Sign-off of HR Reward Calculator |
08-Dec-2015 | Closure |
- Approved budget
- 13.0 days
- Activity this month
- 0.2 days
- Activity this year
- 7.6 days
- Activity to date
- 7.6 days
- Estimate to complete current year
- 5.3 days
- Estimate to complete future years
- 0.0 days