The code work will include extract, XML and APEX work.
Work carried forward from HR HESA Staff Return 13/14 project (HRS082):
- 2 JIRAs with a re-estimated estimate of 4 days have been carried forward from 2013/14
- JIRA HRS085-1 - TERMS field is not being populated for a small number of staff that should have a value in this field
- JIRA HRS085-2 - Wrong DATEFHEI held for 752 employees - Modification of the data extract required
The 2014/15 work includes:
- Feedback requirements from HR re field validations affected
- Provide supporting changes to HR database, application and extracts, if required
- Provide supporting changes to HESA, HESA Archive database, application extracts and BI Suite universes, if required
- APEX work where required
Early indications include:
- 5 field changes,
- 1(+) field that needs removed
- 1 (+) field that needs added
- 1 field that needs moved to a different element (table) , which will have repercussions on Archiving
Resources Skills and Cost
This Project will include resources from HR Business Systems, USG Dev, Dev Tech, and Projects
The proposal estimated a total of 40 days with 20 days for 2014/15 and 20 days for 205/16. However there is a 10 day contingency for 2014/15.
Project has been re-estimated on completion of Brief.
The Brief has been re-estimated to 70 days (of which 20 days are carried forward to 2015-16)
The shortfall has been discussed with the Programme Sponsor and Programme Manager and the shortfall has been agreed in principle. The Programme Manager will resolve this. Information will be covered in
- PRICCL Log, Item 49
Further Information
HESA changes required for 14/15
- HESA Changes this year
- HESA’s new requirements for 2014/15
- 2 JIRAs carried over from 13/14 as above