Report for May 2015
- Report Date
- May 2015
Achievements this Period
- Acceptance testing completed
- All deliverables to be delivered with this project deployed to LIVE (with exception of ETime interface changes - HRS083-14)
- New milestones agreed
Issues
- Resource to support UAT of HRS083-14 not yet secured
- Possible Pay29 issue identified
Next Steps
- Complete build for HRS083-14
- Test HRS083-14
- Deploy HRS083-14 to LIVE
- Update FIS documentation after HRS083-14 complete (requires new screen shots)
- Clarify Pay29 issue and resolve
- Deployment signoff to be achieved
- Close
Milestones
| 29-Jun-2015 | Deployment signoff review |
| 06-Jul-2015 | Closure |
The project RAG Status is currently GREEN
- Approved budget
- 65.0 days
- Activity this month
- 13.5 days
- Activity this year
- 53.0 days
- Activity to date
- 53.0 days
- Estimate to complete current year
- 11.0 days
- Estimate to complete future years
- 0.0 days