Report for May 2015

Report Date
May 2015

Achievements this Period

  • Acceptance testing completed
  • All deliverables to be delivered with this project deployed to LIVE (with exception of ETime interface changes - HRS083-14)
  • New milestones agreed

Issues

  • Resource to support UAT of HRS083-14 not yet secured
  • Possible Pay29 issue identified

Next Steps

  • Complete build for HRS083-14
  • Test HRS083-14
  • Deploy HRS083-14 to LIVE
  • Update FIS documentation after HRS083-14 complete (requires new screen shots)
  • Clarify Pay29 issue and resolve
  • Deployment signoff to be achieved
  • Close

Milestones

 

29-Jun-2015Deployment signoff review
06-Jul-2015Closure

 

The project  RAG Status is currently GREEN

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
65.0 days
Activity this month
13.5 days
Activity this year
53.0 days
Activity to date
53.0 days
Estimate to complete current year
11.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Enhancing Employment Removal of HTBN
Code
HRS083
Programme
Human Resources (HRS)
Project Manager
Morna Findlay
Project Sponsor
Martyn Peggie
Current Stage
Close
Status
Closed
Start Date
31-Oct-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Jul-2015
Overall Priority
Normal
Category
Compliance