Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for July 2015 July 2015 GREEN GREEN GREEN BLUE
Report for June 2015 June 2015 AMBER GREEN GREEN AMBER
Report for May 2015 May 2015 GREEN GREEN GREEN GREEN
Report for April 2015 April 2015 GREEN GREEN GREEN GREEN
Report for March 2015 March 2015 AMBER AMBER GREEN AMBER
Report for February 2015 February 2015 RED GREEN GREEN AMBER
Report for January 2015 January 2015 GREEN GREEN GREEN GREEN
Report for December 2014 December 2014 GREEN GREEN GREEN GREEN
Report for November 2014 November 2014 GREEN GREEN GREEN GREEN
Report for October 2014 October 2014 GREEN

Project Info

Project
Enhancing Employment Removal of HTBN
Code
HRS083
Programme
Human Resources (HRS)
Project Manager
Morna Findlay
Project Sponsor
Martyn Peggie
Current Stage
Close
Status
Closed
Start Date
31-Oct-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Jul-2015
Overall Priority
Normal
Category
Compliance