Report for December 2014

Report Date
December 2014

Achievements this Period

  • Deployment to LIVE signed off by stakeholders
  • DR testing carried out successfully on ne TEST environment
  • New DEV environment created and signed off

Issues

  • Additional effort required - to be discussed with Programme Manager

Next Steps

  • Project closure

Milestones

20-Jan-2015ClosureClose

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
136.0 days
Activity this month
23.0 days
Activity this year
142.3 days
Activity to date
147.2 days
Estimate to complete current year
2.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Migrate Oracle HR & Payroll Database to new Infrastructure
Code
HRS081
Programme
Z. Payroll and Pensions (PPP) (closed)
Project Manager
David Watters
Project Sponsor
Terry Fox
Current Stage
Close
Status
Closed
Start Date
19-Jun-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
02-Feb-2015
Programme Priority
4
Overall Priority
Normal
Category
Compliance