February Monthly Report

Report Date
February 2014

 

Achievements this period
  • Phase 1 Deployment Sign Off review due 10-Feb-14
  • Phase 2 release delayed by Oracle
  • Replan Phase 2
  • Confirm amended Phase 2 milestones
  • Confirm amended Phase 2 ASTA bookings
  • P2 Dev Patching Complete and Signed off - milestone withdrawn
  • Phase 2 patch released 28-Feb-14

Issues

  • Issue with TEST patching being investigated and a service request is being progressed with Oracle

 Next steps

  • P2 Design/Planning (TYE and Legislative sor Start of YR)
  • P2 TEST patching complete and signed off
  • P2 Go Live 19-20th March (length of downtime still to be confirmed)

 Milestones

03-Mar-201420-Feb-2014Phase 2 - Design/Planning (TYE and Legislative for start or Yr)
14-Mar-201405-Mar-2014Phase 2 - TEST Patching Complete and Sign Off
24-Mar-201411-Mar-2014Phase 2 - LIVE Patching Deployment
04-Apr-201418-Apr-2014Phase 2 - Deployment Sign Off
11-Apr-201411-Apr-2014P2 DEV CLONE
12-May-201402-May-2014Phase 3 - Planning/Design (Critical Post Budget Changes - if Req)
16-May-201416-May-2014Phase 3 - DEV Patching Complete and Signed Off
30-May-201430-May-2014Phase 3 - TEST Patching Complete and Sign Off
06-Jun-201406-Jun-2014Phase 3 - LIVE Patching Deployment
20-Jun-201420-Jun-2014Phase 3 - Deployment Sign Off
27-Jun-201427-Jun-2014Project Closure

 

 

Project Status
RAG Status
Overall
AMBER
Change Status
Activity
Approved budget
148.0 days
Activity this month
39.0 days
Activity this year
83.0 days
Activity to date
83.0 days
Estimate to complete current year
72.0 days
Estimate to complete future years
0.0 days

Project Info

Project
HR & Payroll Annual Maintenance 13/14
Code
HRS075
Programme
Human Resources (HRS)
Project Manager
Anne Mathison
Project Sponsor
Terry Fox
Current Stage
Close
Status
Closed
Start Date
24-Sep-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Programme Priority
1
Overall Priority
Normal
Category
Compliance