March Report
- Report Date
- March 2013
Report by Anne Mathison for March 2013
Achievements in Last Period -
- Release to TEST re Phase 2 TYE & RTI completed 5th March
- UAT for Phase 2 for TYE & RTI completed on 6-7th March
- UAT was not signed off by the Business due to some payroll processing occurring twice, so the Go Live planned for 11-12th March was cancelled and delayed until issues were sorted.
- Rescheduled for later in March
- Milestones and estimates revised for remaining Phase 2 pieces of work
- P2 TYE & RTI signed off in LIVE 27th March.
- Unplanned Urgent AE Patch required. Completed in DEV on 27th March and signed off 27th March
- Unplanned Urgent AE Patch required. Completed in TEST on 28th March and signed off on 29th March
- Unplanned Urgent AE Patch required. Completed in LIVE on 1st April and signed off on 1st April
Issues
- P2 P60 coded however had an issue and has been raised with Oracle
- First unplanned Auto-enrolment work was required as soon as possible and had to be accommodated before the tight P2 TYE + RTI patches deadlines.
- This then reduced the time available for TYE + RTI in Dev and Test
- Separating out and replanning the P2 Security patches
- Delaying implementing the P60 work
- Original TYE & RTI work was delayed deploying to LIVE from 11th-12th March to 26-27th March
- HR Globals caused errors when completing patches, however this was resolved in time for the go LIVE implementation of TYE & RTI on 26-27 March.
- Unplanned Urgent TYE + RTI required patch arrived 25-Mar-13 also required for Phase 2 go LIVE - was progressed after the TYE & RTI on 26-27 March and progressed in time to go LIVE 1st April
Next Steps
- P2 P60 with Oracle, hope to have resolved during April - no down time required.
- P3 JRE patches and Password change scheduled for April, DEV 3rd April, TEST 9th April and LIVE 2nd May.
- P3 more RTI patches and Security Patches planned during May
Milestones
02-Apr-2013 | 2 Deploy TYE and RTI Patches plus Urgent AE Patch |
30-Apr-2013 | 2 P60 Live |
03-May-2013 | JRE and Password change |
09-May-2013 | 3 Build RTI Changes + Security patches |
28-May-2013 | 3 ASOR RTI Changes + Security Patches |
03-Jun-2013 | 3 Deploy RTI Changes + Security |
31-Jul-2013 | Closure |
- Approved budget
- 165.0 days
- Activity this month
- 29.0 days
- Activity this year
- 126.0 days
- Activity to date
- 126.0 days
- Estimate to complete current year
- 43.0 days
- Estimate to complete future years
- 0.0 days