Monthly Report
- Report Date
- October 2012
Report by Anne Mathison
Achievements in Last Period
- Started the Planning process based on HMRC Real Time Information (FIN082) ToR and becoming up to date on the expectations with the evolving Tax Year End and Real Time project
Issues
- It is likely that the same resources from the HR systems team and IS Configuration Teams will be required for this project and also eRecruitment, R12 Upgrade, HR HESA Staff Return 12/13
Next Steps
- The Planning Stage is underway and the Brief is expected to be produced by 16th October.
- Approved budget
- 148.0 days
- Activity this month
- 2.0 days
- Activity this year
- 2.0 days
- Activity to date
- 2.0 days
- Estimate to complete current year
- 147.0 days
- Estimate to complete future years
- 0.0 days