Monthly Report

Report Date
October 2012

 

Report by Anne Mathison

Achievements in Last Period

  • Started the Planning process based on HMRC Real Time Information (FIN082) ToR and becoming up to date on the expectations with the evolving Tax Year End and Real Time project

Issues

  • It is likely that the same resources from the HR systems team and IS Configuration Teams will be required for this project and also eRecruitment, R12 Upgrade, HR HESA Staff Return 12/13

Next Steps

  • The Planning Stage is underway and the Brief is expected to be produced by 16th October.

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
148.0 days
Activity this month
2.0 days
Activity this year
2.0 days
Activity to date
2.0 days
Estimate to complete current year
147.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Oracle HR & Payroll Annual Maintenance 12/13
Code
HRS072
Programme
Human Resources (HRS)
Project Manager
Anne Mathison
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
24-Oct-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
11-Nov-2013
Programme Priority
1
Overall Priority
Normal
Category
Compliance