Update 5th August

5th Aug - New patch arrived last week, has been patched into DEV and TEST today includes HR Globals

Kathy to check out, then need to plan which day it goes LIVE.

Down time 2- 5 this afternoon plus add on last week patch 1.5 hours, so down time may be 4.5 hours. - to be confirmed 0.65 of a day.                                                                                                                                                                                                                                                                                                                                                                            Monday 5th Aug put new patch to DEV AM and to TEST PM. Wed 8th Aug,                                                                     Screen change for Payroll put unto TEST and LIVE on Wed 7th Aug.

All 3 RTI patches and API work went Live Thursday 8th Aug

Project Info

Project
Oracle HR & Payroll Annual Maintenance 12/13
Code
HRS072
Programme
Human Resources (HRS)
Project Manager
Anne Mathison
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
24-Oct-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
11-Nov-2013
Programme Priority
1
Overall Priority
Normal
Category
Compliance