Urgent Patch arrived 4/03 for TYE/RTI

Tax threshhold correction for TAX year end

Went to Dev Wed 6th March. HR Globals worked first time

Now going to TEST 7th March after HR set up 2 test items for Kathy.

Kathy testing between Thurs afternoon and Saturday and will send an email out for signoff or problem.

Plan to start11th March (after any prep done 8th Mar pm)

If ok patching going ahead 11-12th March

 

Payroll 3 reports not updated, however the data has been. Go LIVE delayed

Project Info

Project
Oracle HR & Payroll Annual Maintenance 12/13
Code
HRS072
Programme
Human Resources (HRS)
Project Manager
Anne Mathison
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
24-Oct-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
11-Nov-2013
Programme Priority
1
Overall Priority
Normal
Category
Compliance