Impact

Priority and Funding

This Compliance project has normal priority.

It must be noted that the project has been broken into two phases, a procurement and an implementation stage. 

All aspects of Information Services, both during Phase One Procurement and Phase Two Implementation are Core funded from the Corporate Services Group. 

Any Third Party Solution will be funded by the Business (H&S / Fire Safety Unit).

Both will require careful analysis and potentially an amount of re-planning at key points, the following milestones have been added to facilitate this: 

Both could see a requirement to re-analyse / plan the project, particularly in terms of its timeline, resource and budget, if this is the case this will be handled utilising change management procedure.  

There is also the chance that the Project itself could be subject to reappraisal or even closure if suitable responses / solutions cannot be found, the following exit points have been identified to track / help facilitate this:

The total IS / Compliance budget for this Project is 284 days, split across the 2018/19 and 2019/20 financial years.  

Year Estimate at 19/20 Planning Review    Revised Estimate   
2018/19 Estimate   140 144
2019/20 Estimate   60 140

Please note that this estimate is based on procurement of a internally hosted solution and the development of potential interfaces with existing UoE systems, eg. Estates Archibus system for building data.  It should be noted that implementation costs would likely decrease if a SaaS solution is discovered and/or there was no development requirement; 

  • Saas solution could reduce estimate by around 15 days 
  • No development resource could reduce the estimate by around 14 days 

A PICCL #1: Budget Readdress After Planning has been raised over the estimated increase to budget after planning.

 

Impact and Dependencies

This project will have no known impact on any existing operational systems on inception, though if during analysis it is deemed that integration into other systems would be beneficial, for instance to retrieve golden copy of building data, or assets for example, then this could be considered.  Risk #7 System Integration to Obtain Data Could be Required has been raised to track the risk to budget / the current proposed timelines.

There is the distinct possibility that after analysis / procurement that a number of Business processes and / or policies may be subject to change.  Risk #3 After the Procurement Phase it is Possible that an Appropriate Solution / System is not Discovered has been raised to track this.

 

Project Risks

Ref Title Initial Risk Current Risk Status Management Approach Risk Owner Date of Last Review  
1 Project Budget insufficient to complete the project GREEN GREEN Open Retain Candice Schmid 10-Jan-2019

 view

2 After the Procurement Phase There Might Not Be Sufficient Budget to Procure an Appropriate Solution / System GREEN GREEN Open Retain Candice Schmid 10-Jan-2019

 view

3 After the Procurement Phase it is Possible that an Appropriate Solution / System is not Discovered GREEN GREEN Open Retain Candice Schmid 10-Jan-2019

 view

4 Business Requirements are not fully captured ahead of the Procurement Phase GREEN GREEN Open Reduce Andy Mackay 10-Jan-2019

 view

5 Securing Application Development Resource GREEN GREEN Open Reduce Paul Mcnulty 10-Jan-2019

 view

6 Availability, Engagement and buy in of Key Business Resource GREEN GREEN Open Reduce Candice Schmid 10-Jan-2019

 view

7 System Integration to Obtain Data Could be Required AMBER AMBER Open Retain Dave Berry 14-Jan-2019

 view

8 The Procurement Process Takes Longer Than Anticipated GREEN GREEN Open Reduce Candice Schmid 14-Jan-2019

 view

 

 

 

Project Info

Project
Fire Safety Management System Procurement
Code
HAS005
Programme
Health & Safety (HAS)
Management Office
ISG PMO
Project Manager
Richard Bailey
Project Sponsor
Candice Schmid
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
03-Dec-2018
Planning Date
11-Jan-2019
Delivery Date
27-Sep-2019
Close Date
20-Sep-2019
Programme Priority
1
Overall Priority
Normal
Category
Compliance

Documentation

Plan