Weekly update w/c 27/07/2015

  • Development work continuing on iteration 4
  • The 2nd developer still has not been released by the Accommodation Services project. As this project was funded in advance then the lost days will need to be credited in 15/16.  This has been escalated to the CSG Portfolio Manager.
  • Iteration 4 closure review held
  • Both eExpenses developers are on leave next week so the end of iteration go-live has been deferred to w/c 10th August
  • Development work will continue on related eAuthorisations changes next week
  •  

Project Info

Project
eExpenses Phase 2
Code
FIN102
Programme
Finance (FIN)
Project Manager
Dawn Holmes
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
16-Mar-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
18-Sep-2015
Category
Discretionary