Organisation

 

Work/Task Breakdown

The project will be delivered iteratively.  It will open with formal Business Analysis and System Design stages.  These will be followed by a series of development iterations, with each iteration delivering working software fit for release to users.  The overall phases are as follows: -

  • Planning
  • Business Analysis
  • System Design
  • Development Iterations:
    • Build
    • Integrate
    • UAT Test
    • Deploy
  • Closure  

Resources Skills and Cost

The project will be delivered to a fixed cost of 157 IS Applications days.  Key to the project's success is the availability of the System Designer from the original eTime project.  The System Designer will create the revised design, specify the code changes, and support the new developer throughout the Build and Testing stages.

The Planning stage estimates for ISA effort are linked below.

 

Project Info

Project
eTime Phase 3
Code
FIN085
Programme
Finance (FIN)
Project Manager
Jill Nicoll
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
25-Feb-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
16-Jun-2014
Overall Priority
Normal
Category
Compliance