Organisation

Work/Task Breakdown

IS will provide:

  • Project Management (Project Services Programme Manager & Project Manager)
  • Governance via WIS & Communications Plan (Project Services Senior Supplier)
  • Business Analysis (Project Services Business Analyst)
  • Technical Oversight (Enterprise Architect)

Suppliers will provide:

  • Configuration of proprietary software and hardware, & supporting documentation
  • Trial licence

Estates will provide:

  • Governance via Project Board
  • Business Requirements, Business Processes, Document Templates, Report Formats  & other  Design Inputs
  • Review and Sign off of documentatio

 

Resources, Skills and Costs

 

 

Project Governance

Meeting

Purpose

Frequency

Project Board

Formal Project Board for Senior stakeholder update & decision making on Changes, Risks and Issues.

Every 6 to 8 weeks

WIS

Governance body for IS to request approvals for project progression & necessary resource.

Submissions are accepted Fortnightly

Project Touchdown Meeting

All active project delivery personnel to give progress update, agree next steps and raise and review risks and issues.

Weekly

 

Project Stakeholders

Name

Business area

Role

Alan Sloan

ITI Infrastructure

ITI Infrastructure Support

Dave Berry

IS Applications Enterprise Architecture

Enterprise Architect

David Brook

Estates Security

Project Sponsor

Derrick Matheson

IS

Portfolio Manager

Grant Ferguson

Estates Management Group

Director of Estates Management

James Broomfield

Estates Security

Security Manager

Stefan Kaempf

IS Applications Production Management

Senior Supplier

Terry Gillan

Estates Security

Business Lead & Senior User

Sandra Kinnear

ACE Property

Health, Safety and Sustainability Officer

Andrew Glass

ACE Support Services

IT Services Officer

Jimmy Burns Health & Safety Deputy Fire Safety Advisor
Vanessa Dawson IS Programme manager

 

Project Estimations

The estimate for IS resources is:

 

 

Actual spend so far

Estimated future spend

ESTS119 (FY 18):

 

7.5

79

TOTALS

 

7.5

79

 

Link to Estimations Log on Project Web Site: 

 

Project Info

Project
Estates Security System Integration
Code
ESTS119
Programme
Estates Operations Optimisation (EOO)
Management Office
ISG PMO
Project Manager
Derrick Matheson
Project Sponsor
David Brook
Current Stage
Plan
Status
Suspended
Project Classification
Transform
Start Date
03-Sep-2018
Planning Date
28-Sep-2018
Delivery Date
29-Mar-2019
Close Date
19-Apr-2019
Programme Priority
2
Overall Priority
Normal
Category
Discretionary

Documentation

Plan