Report for March 2019

Report Date
March 2019

Server delivered and being configured by IS Devtech team.

 

Estates engaged with making connections between GPS-enabled radios and the Linktel-provided cloud service.

 

Expect to close out remaining activities in April '19

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Within Tolerance
Cost
Within Tolerance
Scope
Within Tolerance
Overall
Within Tolerance
Has formal escalation taken place?
No
Activity
Approved budget
48.0 days
Activity this month
1.0 day
Activity this year
5.5 days
Activity to date
5.5 days
Estimate to complete current year
42.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Estates Security Radio Systems
Code
EST118
Programme
Estates Operations Optimisation (EOO)
Management Office
ISG PMO
Project Manager
Derrick Matheson
Project Sponsor
James Broomfield
Current Stage
Initiate
Status
In Progress
Start Date
15-Oct-2018
Planning Date
25-Jan-2019
Delivery Date
22-Mar-2019
Close Date
10-May-2019
Programme Priority
3
Overall Priority
Normal
Category
Discretionary