Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for December 2019 December 2019 GREEN GREEN GREEN GREEN Within Tolerance
Report for November 2019 November 2019 GREEN GREEN GREEN GREEN Within Tolerance
Report for October 2019 October 2019 GREEN GREEN GREEN GREEN
Report for September 2019 September 2019 GREEN GREEN GREEN GREEN
Report for August 2019 August 2019 GREEN GREEN GREEN GREEN
Report for April 2019 May 2019 GREEN GREEN GREEN GREEN Within Tolerance
Report for March 2019 March 2019 GREEN GREEN GREEN GREEN Within Tolerance
Report for February 2019 February 2019 GREEN GREEN GREEN GREEN Within Tolerance
Report for January 2019 January 2019 GREEN GREEN GREEN GREEN No Change
Report for October 2018 October 2018 GREEN GREEN GREEN GREEN No Change
Report for September 2018 September 2018 GREEN GREEN GREEN GREEN No Change
Awaiting response to prioritisation August 2018 GREEN GREEN GREEN GREEN

Project Info

Project
Estates Security Radio Systems
Code
EST118
Programme
Estates Operations Optimisation (EOO)
Management Office
ISG PMO
Project Manager
Derrick Matheson
Project Sponsor
James Broomfield
Current Stage
Initiate
Status
In Progress
Start Date
15-Oct-2018
Planning Date
25-Jan-2019
Delivery Date
22-Mar-2019
Close Date
10-May-2019
Programme Priority
3
Overall Priority
Normal
Category
Discretionary

Documentation