Organisation

Work/Task Breakdown

 Planning

  • Confirm project brief with the project sponsor and project team
  • Complete project estimate
  • Prepare project plan
  • Sign-off planning phase

 

Systems Design

  • Clarification on current system configuration
  • Review and consolidate upgrade instructions
  • Update Technical Architecture Document (TAD)

 

  • Build/ Configure Phase
  • Business to confirm that TEST system is working as expected prior to upgrade
  • Take a copy of the LIVE database and data and apply to TEST
  • Complete User testing following copy from LIVE to TEST
  • Upgrade the TEST system and document process
  • Reveiw estimate following TEST upgrade to ensure robust

 

User Acceptance Phase

  • Complete user acceptance testing 
  • Investigate where required
  • Complete Implementation Plan and Implementation Record
  • Complete Deployment check List
  • Sign-off User Acceptance Phase

 

Deployment Phase

  • Business to confirm that system is working as expected prior to upgrade
  • Take a copy of the LIVE environment
  • Deploy to LIVE/ production environment
  • Complete post deployment checks
  • Sign-off Deployment Phase

 

Resources Skills and Cost

This project will utilise resources from;

Security Team - system administration and user testing IS Apps Project Services - project mangement IS Apps Development Technology - investigate requirements, carry out a copy from LIVE and upgrade both the TEST and LIVE environments IS Apps Production Management - will provide on-going system support, approve TAD and all support documents  

Project Info

Project
Perspective Upgrade
Code
EST089
Programme
Estates General Programme (EST)
Project Manager
Andrew Stewart
Project Sponsor
Frank Henzell
Current Stage
Close
Status
Closed
Start Date
21-Sep-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
03-Jun-2016