Remaining Work
- Agree that once DM's and PM's have loaded information onto SharePoint that they have seen how to get on to the pilot test site
- Once Adrian, Jason and Shona have gone through the drawing decision and decided that that is appropriate and complete.
- That Adrian shows Catherine too so that she is aware of the process and can include it in her Estates SharePoint Manual
- Adrian has completed his System reference information document for IS Apps and sent a copy to Stephen Smith
- Agree revised milestones and that sign off of what they will include, assuming that 2-3 weeks for DPM's EDM's is completed by the 28th March
- Then signoff at the 24-Mar meeting
WIS 20-May comments from Closure
WIS notes: Approved however some of the narrative in report needs to be clearer and aligned to project brief to aid understanding, to be reviewed with Project Manager.