Work/Task Breakdown
Planning
- Confirm project brief with the project sponsor and the project team incorporating
- project estimate
- project plan
- Secure resource bookings within ASTA
System Design
- Produce updated Technical Architecture Document
- detail interface/cron/user dependancies.
Build Phase - DEV
- Prepare test script
- Confirm that the existing DEV WebCentral system is functioning as expected using the prepared test script.
- Produce Migration plan.
- Migrate DEV Webcentral to the new Infrastructure.
- Test application with database switchover.
User Acceptance - DEV
- Complete user acceptance testing to ensure that TEST WebCentral is functioning as expected
- Sign-off DEV build
Build Phase - TEST
- Confirm that the existing TEST WebCentral system is functioning as expected using the prepared test script.
- Migrate TEST Webcentral to the new Infrastructure.
User Acceptance - TEST
- Complete user acceptance testing to ensure that TEST WebCentral is functioning as expected .
- Update Operations section in TAD.
- Complete Deployment Check List.
- Complete handover to IS Applications Production.
- Sign-off User Acceptance Testing.
Deployment
- Migrate Live Webcentral to new infrastructure.
- Confirm system functioning as expected
- Sign-off deployment
Resource Estimates and Costs
Internal
Resources wiill be required from the following teams;
- Estates and Buildings Energy Team to oversee all system testing
- IS Development Technology to carry out migrations of all environments, update all technical documentation, overseee DR testing( and provide handover to IS Applications Production.
- IS Applications Management to assist with basic connectivity testing on all three environments and complete the Deployment check list
- IS Technical Management to oversee DR testing on Test.
External
- Need to check with external supplier re. implications (if any) of moving to Linux.