Achievements in Last Period
During this period;
Due ot the ongoing uncertainty of when a new Licemsing Model would be agreed, the PM , with the agreement of the Senior User and Programme Manager, submitted a proposal to WIS to descope the remaining deliverables from the project and move the project to the closure stage. The proposal was approved by WIS on 19th December 2014.
https://www.projects.ed.ac.uk/project/est081/issues/2
https://www.wiki.ed.ac.uk/display/insite/Applications+WIS+Notes+-+19th+December+2014
Issues
- No outstanding issues.
Next Steps
- Create project closure report
- Obtain project closure sign-off from stakeholders
- Obtain project closure approval from WIS
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days