November 2014

Report Date
November 2014

 

Achievements  in Last Period

During this period;

  • The User Acceptance Testing of the upgraded Test system was completed and signed-off by Estates
  • The Live system was upgraded to the new version of the software and signed-off by Estates
  • The mandatory deliverables of the project have been achieved.
  • The new licensing model has still to be agreed so work on the remaining tasks has been suspended until the agreement is in place
  • A new milestone for the licensing model agreement was set for 5th December 2014

 

Issues

  • The remaining tasks and milestones need to be re-planned w/c Mon 8th December. 
  • It has not been possible to secure agreement regarding the licensing of the Remote Alarm Monitor licensing with the supplier for the server installation.  This currently resides on the network dongle.

 

Next Steps

  • Review  status of license agreement and determine on the basis to proceed
  • Implement and test the new licensing model in the Test and Live environments
  • Undertake disaster recovery test on the live environment

 

As there is now an uncertainty regarding agreement being reached regarding the Licensing of the Remote Alarm Monitor wit regards to the decision milestone, this project has been assigned a Red RAG status

 

 

Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
GREEN
Overall
RED
Change Status
Activity
Approved budget
15.0 days
Activity this month
2.2 days
Activity this year
4.9 days
Activity to date
4.9 days
Estimate to complete current year
10.2 days
Estimate to complete future years
0.0 days

Project Info

Project
Schenider Sigma BEMS Upgrade
Code
EST081
Programme
Estates General Programme (EST)
Project Manager
Neil Grant
Project Sponsor
Dougie Williams
Current Stage
Close
Status
Closed
Start Date
01-Oct-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Jan-2015
Programme Priority
5
Overall Priority
Normal
Category
Discretionary