Monthly Progress Report
- Report Date
- January 2015
Project is increasing the project team to include Trades team representatives from the 4 zones
Achievements
- Completed and sign-off the Business Requirements document
- Continued collation of the required system configuration data
- First of the monthly communication bulletins and zone briefings drafted and sent to a portiion of managers
Issues
- The proof of concept has been held up due to the timeout Archibus issue. This has been raised with MASS who will be following up with Archibus
Next Steps
- Further 1 day training is planned for 13-Feb for project team members completing the system admin configuration
- Overview for the new project team members (trades) (5-Feb)
- Project team to include 4 trades team members (1 from each zone) to ensure the system will be fit for purpose
- Once the issue has been resolved then the system configuration will be able to continue
- The Proof of Concept for a small number or faults of different types, skills and zones to have been proved in February, before wider consultation in March
The project has been assigned a RAG status of AMBER
Milestones:
13-Mar-2015 | Proof of Concept |
17-Apr-2015 | Acceptance |
15-May-2015 | System Configuration |
26-Jun-2015 | User Training |
30-Jun-2015 | Deliver |
17-Jul-2015 | Deployment Signoff Review and Closure |
- Approved budget
- 145.0 days
- Activity this month
- 17.0 days
- Activity this year
- 77.0 days
- Activity to date
- 77.0 days
- Estimate to complete current year
- 68.0 days
- Estimate to complete future years
- 0.0 days