Report for April 2017
- Report Date
- April 2017
Achievements in Last Period
- As part of the process to continue reviewing the outstanding issues,
- The monthly billing has been successfully implemented
- The remaining issues have been reviewed and decisions taken to move these to a new Jira issue log for further review in version 23.1
- a total of 12 issues have been closed
- review of remaining issues held with Mass on a weekly basis
Issues
- Monthly billing, whilst now in operation, a few issues relating to the processing of archived invoices and credit notes have arisen and are currently being investigated.
Next Steps
- Requirement to resolve the priority issues (noted below) and as many of the non-priority issues prior to closing the project in the next month
- Changing Status on work request (currently under test)
- Correct Employee-Id on weekly download (if now deemed as required)
- Close project
- Continue planning for version 23.1 upgrade incorporating technical aspects from the Lessons Learned report
- Approved budget
- 567.0 days
- Activity this month
- 7.0 days
- Activity this year
- 357.0 days
- Activity to date
- 579.0 days
- Estimate to complete current year
- 5.0 days
- Estimate to complete future years
- 0.0 days