Report for February 2017
- Report Date
- February 2017
Achievements in Last Period
- PPM successfully run on the live environment
- As part of the process to continue reviewing the outstanding issues,
- further 6 issues have been closed
- review of remaining issues held with Mass
- a further 3 fixes have been received and applied, but will require a further tomcat re-start to implement the changes
- requirement for business to review and determine strategy regarding the individual issues
- Monthly billing UAT completed successfully on Test
- Initial DSOR meeting held with IS Applications Management - no performance or functional concerns with the live service
- Project completion report completed and circulated
- Lessons learnt process has commenced
- Andy Stewart has been assigned as project manager to close out the project
Issues
- Unexpected issue encountered on the webcentral url which prevented approval of multiple jobs and the inability to assign a craftsperson a work request. Resolved after a tomcat re-start
- Monthly billing process not signed off as issues encountered whilst running in the live environment
- 21 issues remain on the current outstanding list
- Delays in delivery of EST092 Operational Reports.
- Additional budget will be required to complete the project
Next Steps
- Requirement to re-plan remaining project activities
- Complete Monthly billing UAT, and implement
- Complete Lessons learned
- Continue to focus on closing the appropriate outstanding issues for this project
- Complete Deployment Sign-off and Closure
- Approved budget
- 505.0 days
- Activity this month
- 30.1 days
- Activity this year
- 327.8 days
- Activity to date
- 549.6 days
- Estimate to complete current year
- 17.3 days
- Estimate to complete future years
- 0.0 days