Monthly Progress Report

Report Date
September 2014

 

During the month the focus has been on completing the planning phase of the project

Achievements

  • The Project Brief has been completed to incorporate

    • Project plan and resourcing requested

    • Project estimate established
    • Project Milestones planned and completed in Project Website and ASTA
    • Initial fact finding meeting held
  • The project brief was subsequently approved and signed-off by the project team and project sponsor at a meeting on 9th October

Issues

  • As a result of the project planning phase, the project estimate has been estimated significantly higher than the original estimate generated through the annual planning phase.Having initially been defined as a small project relating to 50 days, the project has been re-estimated at 95 days.  This increase in budget has been approved by the project sponsor and programme owner.

Next Steps

  • Project resourcing assigned
  • Commence  Business Analysis phase
    • Review existing processes and data
    • Requirements gathering

 

 Having now successfully completed the planning phase of the project, the project has been assigned a RAG status of Green

Milestones

DateMilestone
10-Oct-2014Planning (Brief)
07-Nov-2014Business Analysis Milestone
21-Nov-2014Design Milestone (TAD)
05-Dec-2014Configure On Demand (Build)
12-Dec-2014Integration
03-Feb-2015Acceptance
18-Mar-2015Deployment and Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
40.0 days
Activity this month
10.0 days
Activity this year
10.4 days
Activity to date
10.4 days
Estimate to complete current year
84.7 days
Estimate to complete future years
0.0 days