Monthly Progress Report
- Report Date
- September 2014
During the month the focus has been on completing the planning phase of the project
Achievements
The Project Brief has been completed to incorporate
Project plan and resourcing requested
- Project estimate established
- Project Milestones planned and completed in Project Website and ASTA
- Initial fact finding meeting held
- The project brief was subsequently approved and signed-off by the project team and project sponsor at a meeting on 9th October
Issues
- As a result of the project planning phase, the project estimate has been estimated significantly higher than the original estimate generated through the annual planning phase.Having initially been defined as a small project relating to 50 days, the project has been re-estimated at 95 days. This increase in budget has been approved by the project sponsor and programme owner.
Next Steps
- Project resourcing assigned
- Commence Business Analysis phase
- Review existing processes and data
- Requirements gathering
Having now successfully completed the planning phase of the project, the project has been assigned a RAG status of Green
Milestones
Date | Milestone |
10-Oct-2014 | Planning (Brief) |
07-Nov-2014 | Business Analysis Milestone |
21-Nov-2014 | Design Milestone (TAD) |
05-Dec-2014 | Configure On Demand (Build) |
12-Dec-2014 | Integration |
03-Feb-2015 | Acceptance |
18-Mar-2015 | Deployment and Closure |
- Approved budget
- 40.0 days
- Activity this month
- 10.0 days
- Activity this year
- 10.4 days
- Activity to date
- 10.4 days
- Estimate to complete current year
- 84.7 days
- Estimate to complete future years
- 0.0 days