Monthly Report

Report Date
January 2017

Achievements in Last Period

  • Acceptance sign-off complete
  • Training complete
  • Legacy UAT complete
  • Migration SOE complete
  • Estates Helpdesk system LIVE.

Issues

  • Monthly billing process not signed off.
  • Some smaller items still to be delivered as part of project wrap-up. 
  • Delays in delivery of EST092 Operational Reports.

Next Steps

  • Complete Monthly billing UAT, and implement
  • Project completion and Lessons learnt. 

The project is reporting GREEN.  

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
505.0 days
Activity this month
52.2 days
Activity this year
290.7 days
Activity to date
512.5 days
Estimate to complete current year
23.2 days
Estimate to complete future years
0.0 days