Monthly Report
- Report Date
- January 2017
Achievements in Last Period
- Acceptance sign-off complete
- Training complete
- Legacy UAT complete
- Migration SOE complete
- Estates Helpdesk system LIVE.
Issues
- Monthly billing process not signed off.
- Some smaller items still to be delivered as part of project wrap-up.
- Delays in delivery of EST092 Operational Reports.
Next Steps
- Complete Monthly billing UAT, and implement
- Project completion and Lessons learnt.
The project is reporting GREEN.
- Approved budget
- 505.0 days
- Activity this month
- 52.2 days
- Activity this year
- 290.7 days
- Activity to date
- 512.5 days
- Estimate to complete current year
- 23.2 days
- Estimate to complete future years
- 0.0 days